Completed Projects
C-South Levee Improvements
Elevation of levee to +18' from the Cote Blanche Connection to W 107th St.
Engineer: Angelette Design
Contractor: GIS Construction
D-North Levee Improvement
Elevation of levee to +16' near Leonard J. Miller, Jr. Airport. Area was slightly overtopped during Hurricane Ida.
Engineer: Picciola & Associates
Contractor: Outer Limits Contractors
E-North Levee Improvements
Elevation of levee to +16' behind E 44th St. Area was overtopped during Hurricane Ida.
Engineer: Picciola & Associates
Contractor: GIS Construction
Golden Meadow Lock & Pipeline Floodwall Repairs
Repair of scouring around floodwalls in Golden Meadow from Hurricane Ida. Tie-ins were armored with concrete mats after repair.
Engineer: Picciola & Associates
Contractors: Circle, Construction